Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 06-27-2012, 04:55 AM
joday48 joday48 is offline start and finish dates exceeding duration Windows 7 64bit start and finish dates exceeding duration Office 2010 32bit
Novice
start and finish dates exceeding duration
 
Join Date: Jun 2012
Posts: 24
joday48 is on a distinguished road
Default start and finish dates exceeding duration

Hi all



I'm new to MS project and have lots of things I need to ask but for now I'll start with my most current query!

I have just noticed that many of the tasks in my schedule that have start dates in the past, and have actual work entered against them have the correct duration but the start and finish dates do not match the duration.

Am I right in saying that the finish date is now being calculated based on the remaining duration and honouring it's predecessor link and predecessor finish?

Therefore if a task had 3 days remaining to do and it's predecessor finished on the 02/07/12, the task would finish on the 05/07/12 (based on an 8 hour day with units set to 60%).

The PM has not allowed me to update the schedule and re-schedule tasks. He is now looking at start and finish dates and querying why the start and finish dates often exceed the durations! He wants the start and finish dates to remain the same! From what I am seeing this is not workable is it?

The finish dates are moving to the right because they are slipping and are late, is this correct?

Surely his approach is incorrect? The schedule will move to the right when progress is not made as expected.

When I update schedule and re-schedule tasks, it obviously moves to the right.

When re-scheduling tasks, does project schedule them to the next available date according to links, and resource availability?

Thanks for your help

Jo

Last edited by joday48; 06-27-2012 at 06:13 AM. Reason: Self resolved, want to delete but can't
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
start and finish dates exceeding duration Team Planner-maintaining accuracy in task start and finish times david_23 Project 9 04-19-2012 08:33 AM
start and finish dates exceeding duration baseline duration, start and finsih dates ketanco Project 1 04-09-2012 09:47 AM
remaining duration vs finish date ketanco Project 3 02-17-2012 02:24 PM
start and finish dates exceeding duration duration vs actual start and finish dates ketanco Project 1 12-14-2011 09:06 AM
start and finish dates exceeding duration displaying start and finish times as absolute numbers instead of dates benson.wallace Project 2 12-05-2010 07:22 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:08 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft