Old 06-24-2012, 09:03 PM
sanlen sanlen is offline 5 days/week during planning & 7 days/week during implementation Windows XP 5 days/week during planning & 7 days/week during implementation Office 2007
Novice
5 days/week during planning & 7 days/week during implementation
 
Join Date: Aug 2010
Posts: 1
sanlen is on a distinguished road
Default 5 days/week during planning & 7 days/week during implementation

Hi,

We have working days for our project as below:

1. during the planning stage, we are only working from Monday to Friday.
2. after the planning (implementation), our sub-contractor will be working 7 days a weeks (Monday - Sunday).



I have broken down the activities into different milestones and put in one Ms Project 2010 file. However, i cannot figure out how to tell Ms Project that all planning milestones will be with 5 working days a week and all implementation milestones will be working 7 days a week.

Can you please advise how to get this done?
Reply With Quote
  #2  
Old 06-25-2012, 04:17 PM
JulieS JulieS is offline 5 days/week during planning & 7 days/week during implementation Windows 7 64bit 5 days/week during planning & 7 days/week during implementation Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

The tasks being performed by the contractor will use the contractor's calendar if you create the assignment.

Have you created the 7-day per week base calendar? Did you assign that calendar as the base for the resources?

Julie
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
5 days/week during planning & 7 days/week during implementation Conditional Formatting per Week mrgy05 Excel 2 06-07-2012 10:38 AM
5 days/week during planning & 7 days/week during implementation How to reorder the days of the week Mosey Outlook 2 10-31-2011 06:47 AM
5 days/week during planning & 7 days/week during implementation Work Week: hours vary each day rkc Outlook 1 08-31-2011 01:17 PM
5 days/week during planning & 7 days/week during implementation Calander work week cfawcett22 Outlook 1 08-06-2011 01:46 PM
Change Calendar to 4 day work week J C M Outlook 1 04-28-2011 02:20 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:31 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft