sanlen sanlen is offline 5 days/week during planning & 7 days/week during implementation Windows XP 5 days/week during planning & 7 days/week during implementation Office 2007
Novice
5 days/week during planning & 7 days/week during implementation
 
Join Date: Aug 2010
Posts: 1
sanlen is on a distinguished road
Default 5 days/week during planning & 7 days/week during implementation

Hi,



We have working days for our project as below:

1. during the planning stage, we are only working from Monday to Friday.
2. after the planning (implementation), our sub-contractor will be working 7 days a weeks (Monday - Sunday).

I have broken down the activities into different milestones and put in one Ms Project 2010 file. However, i cannot figure out how to tell Ms Project that all planning milestones will be with 5 working days a week and all implementation milestones will be working 7 days a week.

Can you please advise how to get this done?
Reply With Quote
  #2  
Old 06-25-2012, 04:17 PM
JulieS JulieS is offline 5 days/week during planning & 7 days/week during implementation Windows 7 64bit 5 days/week during planning & 7 days/week during implementation Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

The tasks being performed by the contractor will use the contractor's calendar if you create the assignment.

Have you created the 7-day per week base calendar? Did you assign that calendar as the base for the resources?

Julie
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
5 days/week during planning & 7 days/week during implementation Conditional Formatting per Week mrgy05 Excel 2 06-07-2012 10:38 AM
5 days/week during planning & 7 days/week during implementation How to reorder the days of the week Mosey Outlook 2 10-31-2011 06:47 AM
5 days/week during planning & 7 days/week during implementation Work Week: hours vary each day rkc Outlook 1 08-31-2011 01:17 PM
5 days/week during planning & 7 days/week during implementation Calander work week cfawcett22 Outlook 1 08-06-2011 01:46 PM
Change Calendar to 4 day work week J C M Outlook 1 04-28-2011 02:20 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:31 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft