Joeb Joeb is offline How to use fixed duration, fixed work and have resources/units leveled automatically? Windows 7 64bit How to use fixed duration, fixed work and have resources/units leveled automatically? Office 2010 64bit
Novice
How to use fixed duration, fixed work and have resources/units leveled automatically?
 
Join Date: May 2012
Posts: 5
Joeb is on a distinguished road
Default How to use fixed duration, fixed work and have resources/units leveled automatically?

I am reading manuals and searching the web for two hours but can't find a solution to my problem:

I have a task with a fixed "work" of 20 hours and a duration of 10 days (on average 2 hours a day). Now I want to allocate two resources (employees) to this task and I want MS project to set the unites of these two resources automatically. In this example this would mean that each employee works 1 hour a day on the project (12.5%). But I can't find a way to to this. Also, in case I would change "work" or "duration" I would want the resources/units to be changed automatically too (e.g. if I change work to 40 hours, but duration remains the same, the two employees would have to work 25% of their time on the task).

Any help is highly appreciated!


Joe
Reply With Quote
  #2  
Old 06-23-2012, 09:03 AM
JulieS JulieS is offline How to use fixed duration, fixed work and have resources/units leveled automatically? Windows 7 64bit How to use fixed duration, fixed work and have resources/units leveled automatically? Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hello Joe,
To do the initial calculation of Units, do the following:

Add the 10-day duration task.
Show the Task form in the lower pane (Window > Split) and set the task type as Fixed Duration. Click OK in the Task Form

using the task form, pick the first resource and key 10 hours of work, pick the second resource and key 10 hours of work in the work field. click OK and Project will calculate 13% assignment unit for each resource.

To your second point, you can't do both without a change.

In Fixed duration tasks - if you change Work, Project will change Units.
In Fixed Work tasks -- if you change duration, Project will change units.

in Fixed Duration tasks -- if you change Duration, Project will change Work.
In Fixed Work tasks -- if you change Work, Project will change duration.

So, the moral. Figure out which variable you are going to change, and which variable you want to stay the same -- and set the task type BEFORE making the change.

I hope this helps.

Julie
____________________________
Ah, sorry. I just noticed you are using Project 2010. So -- the Window Split command is now View ribbon, Details check box. Also you'll need to display the Task usage view and add Peak Units to see the 13% assignment units.
Reply With Quote
  #3  
Old 06-25-2012, 12:34 AM
Joeb Joeb is offline How to use fixed duration, fixed work and have resources/units leveled automatically? Windows 7 64bit How to use fixed duration, fixed work and have resources/units leveled automatically? Office 2010 64bit
Novice
How to use fixed duration, fixed work and have resources/units leveled automatically?
 
Join Date: May 2012
Posts: 5
Joeb is on a distinguished road
Default

thank you, i will try this...
Reply With Quote
  #4  
Old 06-25-2012, 04:18 PM
JulieS JulieS is offline How to use fixed duration, fixed work and have resources/units leveled automatically? Windows 7 64bit How to use fixed duration, fixed work and have resources/units leveled automatically? Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome. Post back with further questions as needed.
Reply With Quote
Reply

Tags
duration, units, work

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Roll-Up Duration: Changing Units of Measure & Also Accuracy Of Pmacdaddy Project 3 04-20-2012 07:13 AM
Task duration between 2 fixed milestones cettolox Project 3 01-24-2012 06:33 AM
How to use fixed duration, fixed work and have resources/units leveled automatically? Quick Click not fixed in SP3? implus it Outlook 2 11-09-2011 01:30 PM
How to use fixed duration, fixed work and have resources/units leveled automatically? Time now--fixed? markg2 Excel 1 09-19-2010 12:05 AM
Deleting fixed name on top right of page regularjoeback Word 1 03-23-2010 04:43 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:39 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft