How can I show just day and month but not year, for the start and finish columns? right now it is showing the year also, which I am trying to eliminate.
|
#2
|
|||
|
|||
![]()
ok. nevermind. found my answer... tools, options, view, date format...
|
#3
|
|||
|
|||
![]()
For people using Project 2010:
File, Options, General section. |
![]() |
|
![]() |
||||