ketanco ketanco is offline assiging equipment as resource Windows 7 64bit assiging equipment as resource Office 2007
Expert
assiging equipment as resource
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default assiging equipment as resource

when assiging resources i saw only work, material cost but i didnt see equipment. how can i assign the cost of excavator equipment for example? which type should i use?
Reply With Quote
  #2  
Old 06-08-2012, 01:59 PM
JulieS JulieS is offline assiging equipment as resource Windows 7 64bit assiging equipment as resource Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You have a couple of choices:
You can create the excavator as a work resource, specify the cost per hour on the resource sheet and assign the excavator like a human resource. The work for the excavator will be added to the work for the task.
Downside: it is impossible in project to tie the excavator and excavator operator together and you may end up with the operator working without the excavator and the excavator working without the operator.
If you need to account for the cost of the excavator and also need to make sure your operator and equipment work together, create a resource that stands for both resources together -- for example: Excavator 1 and Bob. Increase the cost for the resource to include both Bob's cost as well as the equipment cost.

If you just need to track costs, and are not concerned about tracking availability, create the cost resource and assign the cost resource to the task.

I hope this helps.

Julie
Reply With Quote
  #3  
Old 06-09-2012, 06:16 PM
ketanco ketanco is offline assiging equipment as resource Windows 7 64bit assiging equipment as resource Office 2007
Expert
assiging equipment as resource
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

by impossible to tie you mean, you can not tie two resources together in ms project right?
Reply With Quote
  #4  
Old 06-10-2012, 03:32 AM
JulieS JulieS is offline assiging equipment as resource Windows 7 64bit assiging equipment as resource Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Yes, you cannot force two resources to work together on a single assignment. Each resource is scheduled on the task based upon his/her calendar.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
assiging equipment as resource how to enter equipment resources benson.wallace Project 5 03-15-2023 01:43 PM
Assiging more than one labor of the same type ketanco Project 5 06-08-2012 01:28 PM
assiging equipment as resource Managing equipment and person operating equipment ProfessorGilligan1 Project 1 04-12-2012 12:29 PM
assiging equipment as resource new name for outlook resource Rayat Outlook 1 07-05-2011 04:12 AM
Resource Calendars caz46 Project 0 02-12-2011 05:31 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:47 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft