In my schedule there were unstarted activities with certain durations based on 5 day regualr calendar.

When I changed my calendar to a 6 day working calendar, those durations remained the same but the finish dates got sooner now. Why did the duration remain the same? How can i make duratino to update automatically when i change from 5 day calendar to 6 day calendar?
Reply With Quote
  #2  
Old 05-22-2012, 07:45 AM
JulieS JulieS is offline changing calendar vs duration Windows 7 64bit changing calendar vs duration Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Because the definition of a "day" or "week" is set in Tools > Options, not through the calendar.

I'm guessing you are using 1 day = 8 hours and 1 week = 40 hours.

Julie
Reply With Quote
  #3  
Old 05-22-2012, 09:02 AM
ketanco ketanco is offline changing calendar vs duration Windows 7 64bit changing calendar vs duration Office 2007
Expert
changing calendar vs duration
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

so it didnt change because the durations represent the number of working days which is the same, but now since i got also saturdays my finish dates moved closer right?
Reply With Quote
  #4  
Old 05-22-2012, 09:57 AM
JulieS JulieS is offline changing calendar vs duration Windows 7 64bit changing calendar vs duration Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Correct. Duration is always measured in working time. So, for example:

The task was originally 4 days long - starting on Wednesday and finishing on the following Monday. Four working days counting Wednesday, Thursday, Friday, and Monday. Saturday and Sunday are not counted in the "4 days" because, unless you have changed the calendar, Saturday and Sunday are non-working days.

You then change the calendar and let Saturday be a working day. The task duration is still 4 days - but now ends on Saturday because Saturday is now a working day.
Reply With Quote
  #5  
Old 05-22-2012, 11:18 AM
ketanco ketanco is offline changing calendar vs duration Windows 7 64bit changing calendar vs duration Office 2007
Expert
changing calendar vs duration
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

but now i made a new calendar with 10 hour workdays and still 5 days a week. but although the finish dates again got closer, the durations remained the same. this time wouldnt the durations change? because those durations were based on a 8 hour workday. but now i have 10 hourt workdays and the durations remained the same. how can this be? and if i need to correct something, what should i correct?
Reply With Quote
  #6  
Old 05-22-2012, 01:04 PM
JulieS JulieS is offline changing calendar vs duration Windows 7 64bit changing calendar vs duration Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

A "day" is still 8 hours. If all of your tasks are based upon a 10 hour work day, you should change the definition of "day" in Tools > Options. Schedule. However, if you have a mixture of calendars, some with 8 and some with 10 hours per day you're going to have to choose one definition.

I suggest stopping talking "duration" and start talking start and end dates if you have mixed calendars.

Julie
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Roll-Up Duration: Changing Units of Measure & Also Accuracy Of Pmacdaddy Project 3 04-20-2012 07:13 AM
changing calendar vs duration total slack not changing when changing duration ketanco Project 1 02-11-2012 07:23 AM
changing calendar vs duration calculating duration ketanco Project 5 12-15-2011 07:15 PM
Work not changing duration benoldays Project 0 02-14-2011 08:21 PM
changing font size without changing leading carolns Word 1 09-14-2009 12:30 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:20 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft