#1
|
|||
|
|||
Finish Variance
Hello,
Finish Variance Column calculates finish date vs baseline finish date. But I later saved Baseline 1, Baseline 2 etc... How can I calculate the difference of finish dates between current finish date vs baseline2 finish date for instance? I couldnt see a column calculating that. Thanks |
#2
|
|||
|
|||
You can select which baseline to calculate Variance from in File > Options, Advanced - Earned Value Options (Project 2010) or Tools > Options, Calculation, Earned Value button (2007 or 2003).
You may also calculate Variance manually in spare Duration field. Use the formula: ProjDateDiff([Baseline1 Finish],[Finish]) to calculate the finish variance using Baseline1 Finish. I hope this helps. Julie |
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Send e-mail message in Finish & Merge | CDTom | Mail Merge | 1 | 08-24-2012 12:52 AM |
remaining duration vs finish date | ketanco | Project | 3 | 02-17-2012 02:24 PM |
First To Finish Task Scheduling | Jody | Project | 6 | 09-23-2011 07:06 AM |
Finish Variance in Resouce Usage View | stct | Project | 3 | 05-17-2011 02:07 PM |
Help with Interim Baseline Variance | poyns | Project | 1 | 05-27-2010 10:59 AM |