I admit my primary project management software is not MSP (P6), but I am fairly proficient at MSP. I just can't figure out how to jump to a successor task. Only way I've figured out to do it is ctrl-G and then enter the task ID. Seems like there should be a better way (there is in P6...) Ideas? |
#2
|
|||
|
|||
Sorry, no. The Task Inspector in Project 2010 allows you to jump to a task's predecessor but not successor.
You may view predecessor and successor information including task name by formatting the task form (View > Details) or may like the Relationship Diagram in the lower pane -- but you cannot "walk" through successors, only predecessors. I hope this helps. Julie |
Tags |
task |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Format template to allow user typing to jump to a new location | dan28029 | Word | 2 | 02-13-2012 06:35 AM |
How do I jump to IE browser during presentation | Steve-O | PowerPoint | 2 | 10-14-2011 01:53 PM |
how to make the task starts next day if no time enough today(task can not be split) | duraid | Project | 1 | 10-25-2010 08:31 AM |
How to Jump Back and Forth? | jjudson | PowerPoint | 1 | 08-02-2009 12:04 AM |
My Subforms jump when I click the tab | jbryanh | Office | 1 | 10-13-2005 07:12 AM |