I admit my primary project management software is not MSP (P6), but I am fairly proficient at MSP. I just can't figure out how to jump to a successor task. Only way I've figured out to do it is ctrl-G and then enter the task ID. Seems like there should be a better way (there is in P6...)
Ideas? |