baseline duration, start and finsih dates
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default baseline duration, start and finsih dates

I am reviewing the schedule our contractor did and it has a baseline duration column, which shows durations. Then I wanted to see the baseline start and finish dates and inserted those columns but it says n/a in those columns for all activities. how is it possible that the activities in his schedule have baseline durations but not baseline start and finish dates?

I checked the set baseline option and it doesnt say anything when baseline was saved so it means he didnt save basline correct? so then baseline start and finish dates showing n/a makes sense however why is there duration values for baseline durations then?
Reply With Quote
  #2  
Old 04-09-2012, 09:47 AM
JulieS JulieS is offline baseline duration, start and finsih dates Windows 7 64bit baseline duration, start and finsih dates Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

It sounds as though he may have just copied and pasted the duration to the baseline duration. When a baseline is saved automatically saved are:
Baseline Start
Baseline Finish
Baseline Duration
Baseline Cost
Baseline Work
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
baseline duration, start and finsih dates baseline duration of summary not updating. why ketanco Project 1 12-14-2011 09:07 AM
baseline duration, start and finsih dates duration vs actual start and finish dates ketanco Project 1 12-14-2011 09:06 AM
baseline duration, start and finsih dates Task Start and End Dates OTPM Project 2 12-04-2011 09:14 AM
start-stop month dates in calendar madison320 Project 0 06-24-2011 08:15 AM
baseline duration, start and finsih dates Setting Drop Dead Start Dates greenboard Project 2 06-14-2010 08:12 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:55 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft