can not delte actual dates in future
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default can not delte actual dates in future

I am trying to review and correct a schedule done by a contractor and he put in actual dates for some activities although they are in the future. I am trying to delete those actual dates. but i can not. i go to that cell and hit delete and nothing happens. He also put in actual durations too. so I tried deleting actual durations too but all it does is to update actual dates but i still can not delete actual dates. please help, how can i delete the actual dates for future activities? on another project schedule i did myself, i cam able to do it but not on the schedule he did.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
can not delte actual dates in future Calendar without actual dates parnol01 Project 1 12-16-2015 09:30 AM
can not delte actual dates in future entering future dates for a project that has started ketanco Project 5 12-15-2011 07:16 PM
can not delte actual dates in future duration vs actual start and finish dates ketanco Project 1 12-14-2011 09:06 AM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM
Stop Future Recurring Meetings mileskb Outlook 0 06-03-2009 04:59 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:47 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft