If you enter work when you assign resources, Project will recalculate duration. As far as how many people - that is up to you when you assign.

Many people enter rough estimates of duration when initially creating tasks and then further refine those duration estimates by assigning resources and their work estimates. As long as the assignment units are accurate (50%, 25%, etc) then you will have durations based more closely on the resource's work estimates and their availability.

Julie
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
How to know the outstanding balance amount of a Loan? PRADEEPB270 Excel 1 01-07-2012 04:45 AM
amount of work Large amount of text as a form field. JustK Word 2 11-15-2011 11:17 AM
Sum required without consider the negative amount PRADEEPB270 Excel 2 08-22-2011 04:23 AM
Analysis of Amount based on following criterion. aligahk06 Excel 1 04-24-2010 10:34 AM
Convert Dollar amount to text GeorgeLawshe Word 0 03-07-2010 10:17 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:24 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft