#1
|
|||
|
|||
![]()
I have a very basic question and I thought I knew this but when I started to think about it, I realized I didnt, because it has been a while since I never used resources on my schedules and I forgot a little...
Lets say you have a task of paint walls. On a schedule that I didnt use any resources, I defined the "size" of this task by simply assiging it a duration. And thats it. But on a schedule that I use resources, how can I do that? If I assign work as 10 hours, does it mean it takes 10 hours to complete this task by...what? 1 person? In other words, how do you define the size of a task? Or, do you just assign say 3 people to the task and its work and duration will be calculated automatically? So you never assign the size of the task yourself but it is calculated? |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
How to know the outstanding balance amount of a Loan? | PRADEEPB270 | Excel | 1 | 01-07-2012 04:45 AM |
![]() |
JustK | Word | 2 | 11-15-2011 11:17 AM |
Sum required without consider the negative amount | PRADEEPB270 | Excel | 2 | 08-22-2011 04:23 AM |
Analysis of Amount based on following criterion. | aligahk06 | Excel | 1 | 04-24-2010 10:34 AM |
Convert Dollar amount to text | GeorgeLawshe | Word | 0 | 03-07-2010 10:17 PM |