pstein pstein is offline How to let the Gantt chart always initially start after the last column on the left? Windows 7 64bit How to let the Gantt chart always initially start after the last column on the left? Office 2007
Novice
How to let the Gantt chart always initially start after the last column on the left?
 
Join Date: Jan 2012
Posts: 29
pstein is on a distinguished road
Default How to let the Gantt chart always initially start after the last column on the left?

When I open the Gantt Chart View of a project then there are currently some columns on the left and the Gantt Chart on the right.

However there is sometimes a (big) space gap between the right-most column and the Gantt Chart part.
Ok I can drag the vertical border so that both parts touch each other.
But the next time I open the project again the gap may re-appear.

How can I tell MS Project 2007 to always automatically let the Gantt pane start initially immediately right of the column part on the left?

Peter
Reply With Quote
  #2  
Old 03-27-2012, 08:01 AM
JulieS JulieS is offline How to let the Gantt chart always initially start after the last column on the left? Windows 7 64bit How to let the Gantt chart always initially start after the last column on the left? Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi Peter,

I'm afraid I don't quite follow your question. Are you saying the split bar keeps moving or the Gantt chart is scrolled so tasks are not visible?

The Gantt chart should open to the view arrangement it was left in. If you are seeing large gaps, is there a gap between your project start date and the first task(s)?

If you press CTRL+ Home and then ALT+Home after opening the file, does that resolve it? Then save, close and re-open -- does it still work?

Julie
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
move to first date on gantt chart etsoft Project 3 12-23-2011 08:32 AM
Showing unscheduled tasks on Gantt chart jaworski_m Project 0 11-20-2011 12:37 AM
How to let the Gantt chart always initially start after the last column on the left? Links to several milestones on same line of a Gantt chart viv_2_k Project 3 08-03-2011 04:40 AM
Exporting Gantt Chart to MS Word 2007 earweed Project 4 06-02-2011 09:21 AM
How to let the Gantt chart always initially start after the last column on the left? Gantt Chart: MS Project vs. Excel Nance Project 2 12-09-2008 01:59 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:38 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft