Hello bluphoto,
Sorry, I don't think you're going to be able to accomplish this using the standard WBS field. The requirements are that subtasks inherit the parent information -- even if you set it to "Characters - unordered". Would using a text field and renaming it WBS do what you need? You'd then need to manually enter the codes for each task -- but you could get exactly what you want. Julie |
|
![]() |
||||