#1
|
|||
|
|||
adjusting remaining work per status date
Hello,
In the following link of ms project site: http://office.microsoft.com/en-us/pr...888.aspx?CTT=3 Please see last sentence that says: "You can set defaults to specify how Project will automatically adjust where actuals and remaining work are placed according to the status date of the project." Can you please clarify and give details about this sentence? I did not understand how or where this is done exactly. |
#2
|
|||
|
|||
The sentence is referring to the options in Tools > Options, Calculation page. Specifically the options:
"Move end of completed parts after the status date back to the status date" "Move start of remaining parts before status date forward tot he status date" |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
remaining duration vs finish date | ketanco | Project | 3 | 02-17-2012 02:24 PM |
Meaning of current date vs status date when saving baselines | ketanco | Project | 1 | 02-08-2012 02:20 PM |
updating status date and actual duration | ketanco | Project | 5 | 01-27-2012 07:32 AM |
MS Project Start Dates not matching the Status Date | sjodom | Project | 3 | 12-04-2011 08:45 AM |
Automatic resouce assignment of remaining unallocated units | philk | Project | 0 | 05-04-2011 04:57 PM |