#1
|
|||
|
|||
How do I get 100 workplans published all at once?
Hi,
Once a week, I have to publish 100 workplans in Project 2012. I was told that maybe there is an easier way to do it than to do one by one. Is it possible to create a macro to performace publishing at an specific time of the day? Thanks in advance! |
#2
|
|||
|
|||
Hi Marcela,
You might have better luck taking a look at the Microsoft forum for Project Server: http://social.technet.microsoft.com/...eneral/threads I imagine it is also possible using PowerShell to automate the publishing process -- however I'm not the person to direct you in that issue. See: http://technet.microsoft.com/en-us/l.../ee662497.aspx Julie |
#3
|
|||
|
|||
Thanks a lot for the advice! I wrote to them. Thanks a again!
|
#4
|
|||
|
|||
You're welcome.
|
|