#1
|
|||
|
|||
Option "Autolink inserted or moved tasks"
Hi,
I set on the Option "Autolink inserted or moved tasks" in File > Options >Schedule but does not seem work. What can i do? I'm using 2010 Ms Project release. thanks. |
#2
|
|||
|
|||
Hi fargo,
Autolink only works if you insert a new task between two tasks which are linked in a F to S relationship. If the link is SS, FF, or SF or has been modified by lead or lag it will not autolink. In what specific scenario are you seeing it not function? i just did a quick test in project 2010 with SP-1 and it works as expected. Julie |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Why the "day" is not inserted as we read values from Excel to Word? | Jamal NUMAN | Word | 8 | 09-04-2011 07:48 AM |
Why the left edge of an inserted table is out "text boundary" by default? | Jamal NUMAN | Word Tables | 2 | 06-30-2011 04:47 PM |
Option "Show picture placeholders" only works for inline pictures?? Fix? | MattM | Word | 2 | 06-15-2011 06:33 AM |
Make "Keep Text Only" the default past option in PP2003 | powerpointbry | PowerPoint | 0 | 09-17-2010 12:48 AM |
merge field formatting problem with "text to be inserted before" | wissam | Mail Merge | 0 | 12-13-2009 12:50 AM |