ALthough I assigned two more predecessors to an activity, which is supposed to delay it further as they finish later, the activitys start date did not change. Why might that be? After that, since it didnt work, I also tried to force a start date however now it is not changing it to the date i am entering. i tried every way of entering. and while it doesnt change it to the date i like, it doesnt give an error either. it just doesnt change the date... which made my schedule 1 year longer !!! do you think i have issues with my software here and what can be done? |
#2
|
|||
|
|||
![]()
There are a number of things that affect the start date of a task. Check for the following:
Actual Start date Constraint other than As Soon As Possible Resources assigned with non-working time in the calendar Lead or lag added to the link relationship |
![]() |
Thread Tools | |
Display Modes | |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Task with Start date but no Due date? | bplat | Outlook | 0 | 01-12-2012 08:10 AM |
![]() |
Antares | Project | 3 | 12-09-2011 03:17 PM |
![]() |
sjodom | Project | 3 | 12-04-2011 08:45 AM |
![]() |
steve138 | Project | 4 | 05-20-2011 04:55 AM |
MS Project able to import actual start and or actual finish date from Excel? | mhacker | Project | 0 | 04-26-2010 11:29 AM |