calculation of start date
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default calculation of start date


Hello,
ALthough I assigned two more predecessors to an activity, which is supposed to delay it further as they finish later, the activitys start date did not change. Why might that be?

After that, since it didnt work, I also tried to force a start date however now it is not changing it to the date i am entering. i tried every way of entering. and while it doesnt change it to the date i like, it doesnt give an error either. it just doesnt change the date... which made my schedule 1 year longer !!!

do you think i have issues with my software here and what can be done?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Task with Start date but no Due date? bplat Outlook 0 01-12-2012 08:10 AM
calculation of start date Groups to be sorted by start date in MS Project Antares Project 3 12-09-2011 03:17 PM
calculation of start date MS Project Start Dates not matching the Status Date sjodom Project 3 12-04-2011 08:45 AM
calculation of start date Project start date steve138 Project 4 05-20-2011 04:55 AM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:22 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft