allocate 0% to resource results in 99% complete ?
As a projectmanager I would like to follow-up all my projects closely.
When defining a recurring task with multiple subtasks dedicated to different people (no deadlines, all 100 or 50/50 % assigned), I mainly put my name in the header as 0% assigned in order to easy look-up on project with my name on it. When date of work is expired, duration equals actual duration and all the amount of work is 100% completed, the amount of work is still set to 99% rather than 100%. This results in an incomplete task although it was completed. When I delete my name (with 0% allocation) in the main header, 99% changes to 100%, and the task is set to complete. Why is this ? Any thoughts ? |
#2
|
|||
|
|||
Generally assigning resources to summary tasks is not recommended. Consider using the "Contact" field or a custom field to store your name.
If a summary task has a milestone (zero duration, zero work) which has not been marked 100% complete -- the summary task will stay at 99% complete. There may be a hiccup occurring that there is still not 100% complete of work on your assignment even though there is no work. Try using another field for lookup for you -- and do not assign yourself (or anyone) to summary tasks. |
#3
|
|||
|
|||
if there is zero work and zero duration for a summary task, how is it possible it would not be be marked as 100% complete but 99% ? is this a bug in project ?
|
#4
|
|||
|
|||
Summary tasks don't have zero duration. Milestones do and having a milestone not marked as 100% complete may cause the 99% complete at the summary task level. It is not a bug -- it would be incorrect of Project to assume a milestone is 100% complete without you marking it so.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
% Complete (Actual) vs % Complete (Should) | Carlos Maximo | Project | 3 | 12-06-2011 12:01 PM |
Search results disappearing | Emerogork | Office | 3 | 07-17-2011 03:52 PM |
Equally allocate/assign across resouces | chconnors | Project | 1 | 06-01-2011 03:27 AM |
Sort by criteria: number of results | p0k | Excel | 1 | 10-22-2009 08:33 PM |
filesaveas method for ms project in c# results in error | mikimik | Project | 0 | 10-12-2006 07:53 AM |