Hi,
I have seen below behaviour:
- A task A got split as there were some actuals before the start date followed by a work done on a different task
-Later there was a changing in project priorities with other project tasks getting higher priorities
- To make sure that half worked task A gets finished before any other task I set its priority to 1000
-Still pending part (after the split) of task A is prioritised after all the tasks having priority less to it! (I use Priority/Standard levelling; no splits allowed)
Why is that? To get around I had to delete actuals for Task A and then re-level.
thanks
Reply With Quote
  #2  
Old 02-25-2012, 07:50 AM
JulieS JulieS is offline Priority based levelling for split tasks having actuals Windows 7 64bit Priority based levelling for split tasks having actuals Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

see my answer in the other forum:

http://tek-tips.com/viewthread.cfm?qid=1675858
Reply With Quote
  #3  
Old 02-26-2012, 11:41 PM
proj12 proj12 is offline Priority based levelling for split tasks having actuals Windows XP Priority based levelling for split tasks having actuals Office 2007
Novice
Priority based levelling for split tasks having actuals
 
Join Date: Feb 2012
Posts: 3
proj12 is on a distinguished road
Default As an example...

To make it simpler to explain, lets take a look at the example I have attached. Tasks 4 to 1 have decreasing priority however due to some reason (common in IT projects), developer thought its smarter to work on some part of task 1 first. hence actuals got recorded for task 1 (typically actuals are recorded twice/thrice a week but full review of tasks happens only once a week as there are 100's). Now when its realised that lets get over with Task1 completely - its too late: even if you change priority of task 1 to 1000 it will not delete the split.
Attached Files
File Type: zip Pending_part_of_split.zip (39.9 KB, 11 views)
Reply With Quote
  #4  
Old 02-27-2012, 06:47 AM
JulieS JulieS is offline Priority based levelling for split tasks having actuals Windows 7 64bit Priority based levelling for split tasks having actuals Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Answer at:

http://tek-tips.com/viewthread.cfm?qid=1675858
Reply With Quote
Reply

Tags
split priority

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Export Excel tasks into Outlook Tasks (2007 Version on both) crazedmom Excel 0 12-29-2011 07:55 AM
the best way to enter actuals ketanco Project 3 12-26-2011 09:36 AM
Priority based levelling for split tasks having actuals Automatically split Mail Merge based on number of pages SaneMan Mail Merge 1 12-03-2011 01:11 AM
Calender month view peeve - display high priority over low priority appts? ghumdinger Outlook 0 07-25-2011 03:56 AM
Priority based levelling for split tasks having actuals actuals vs estimates projectman Project 23 11-15-2010 07:23 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:30 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft