Hi,
I have seen below behaviour: - A task A got split as there were some actuals before the start date followed by a work done on a different task -Later there was a changing in project priorities with other project tasks getting higher priorities - To make sure that half worked task A gets finished before any other task I set its priority to 1000 -Still pending part (after the split) of task A is prioritised after all the tasks having priority less to it! (I use Priority/Standard levelling; no splits allowed) Why is that? To get around I had to delete actuals for Task A and then re-level. thanks |
#2
|
|||
|
|||
![]() |
#3
|
|||
|
|||
![]()
To make it simpler to explain, lets take a look at the example I have attached. Tasks 4 to 1 have decreasing priority however due to some reason (common in IT projects), developer thought its smarter to work on some part of task 1 first. hence actuals got recorded for task 1 (typically actuals are recorded twice/thrice a week but full review of tasks happens only once a week as there are 100's). Now when its realised that lets get over with Task1 completely - its too late: even if you change priority of task 1 to 1000 it will not delete the split.
|
#4
|
|||
|
|||
![]() |
![]() |
Tags |
split priority |
Thread Tools | |
Display Modes | |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Export Excel tasks into Outlook Tasks (2007 Version on both) | crazedmom | Excel | 0 | 12-29-2011 07:55 AM |
the best way to enter actuals | ketanco | Project | 3 | 12-26-2011 09:36 AM |
![]() |
SaneMan | Mail Merge | 1 | 12-03-2011 01:11 AM |
Calender month view peeve - display high priority over low priority appts? | ghumdinger | Outlook | 0 | 07-25-2011 03:56 AM |
![]() |
projectman | Project | 23 | 11-15-2010 07:23 AM |