#2
|
|||
|
|||
![]()
Installations is a successor to Track works with a Start to Start + 1 month lag.
The finish of Installations is a copy/paste link to the value in the start of Testing. Testing is linked Finish to Finish with Track works. |
|
![]() |
||||