ketanco ketanco is offline remaining duration vs finish date Windows 7 64bit remaining duration vs finish date Office 2007
Expert
remaining duration vs finish date
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default remaining duration vs finish date

Hello,


Although I updated the status date of my project to today, february 15th, and i am showing a 10 day remaining duration with manual entry there, the finish date is showing feb 21 for an activity, which is much sooner than 10 days from now. why?
Reply With Quote
  #2  
Old 02-17-2012, 09:26 AM
JulieS JulieS is offline remaining duration vs finish date Windows 7 64bit remaining duration vs finish date Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Updating the status date does not move tasks by itself. You need to run the Reschedule uncompleted tasks command -- which is going to split your task (which you did not like from a previous post) and move the remaining work to be scheduled as of the status date.

Then the remaining duration and the scheduled finish date should align.

Julie
Reply With Quote
  #3  
Old 02-17-2012, 12:55 PM
ketanco ketanco is offline remaining duration vs finish date Windows 7 64bit remaining duration vs finish date Office 2007
Expert
remaining duration vs finish date
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

Quote:
Originally Posted by JulieS View Post
Updating the status date does not move tasks by itself. You need to run the Reschedule uncompleted tasks command -- which is going to split your task (which you did not like from a previous post) and move the remaining work to be scheduled as of the status date.

Then the remaining duration and the scheduled finish date should align.

Julie
yes, from the previous post you are right so is there no way to not split task but still make it longer when you make rescheduling? i mean instead of that split why doesnt it just fill in between the splits? the work did not stop it siomply took longer... is there no way to do that? if not the only way is the fill in bewteen the split portions manually right?
Reply With Quote
  #4  
Old 02-17-2012, 02:24 PM
JulieS JulieS is offline remaining duration vs finish date Windows 7 64bit remaining duration vs finish date Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

If the work took longer than originally planned, you should record Actual Duration and then increase remaining duration.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
updating status date and actual duration ketanco Project 5 01-27-2012 07:32 AM
remaining duration vs finish date duration vs actual start and finish dates ketanco Project 1 12-14-2011 09:06 AM
remaining duration vs finish date First To Finish Task Scheduling Jody Project 6 09-23-2011 07:06 AM
Automatic resouce assignment of remaining unallocated units philk Project 0 05-04-2011 04:57 PM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:12 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft