remaining duration vs finish date
Hello, Although I updated the status date of my project to today, february 15th, and i am showing a 10 day remaining duration with manual entry there, the finish date is showing feb 21 for an activity, which is much sooner than 10 days from now. why? |
#2
|
|||
|
|||
Updating the status date does not move tasks by itself. You need to run the Reschedule uncompleted tasks command -- which is going to split your task (which you did not like from a previous post) and move the remaining work to be scheduled as of the status date.
Then the remaining duration and the scheduled finish date should align. Julie |
#3
|
|||
|
|||
Quote:
|
#4
|
|||
|
|||
If the work took longer than originally planned, you should record Actual Duration and then increase remaining duration.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
updating status date and actual duration | ketanco | Project | 5 | 01-27-2012 07:32 AM |
duration vs actual start and finish dates | ketanco | Project | 1 | 12-14-2011 09:06 AM |
First To Finish Task Scheduling | Jody | Project | 6 | 09-23-2011 07:06 AM |
Automatic resouce assignment of remaining unallocated units | philk | Project | 0 | 05-04-2011 04:57 PM |
MS Project able to import actual start and or actual finish date from Excel? | mhacker | Project | 0 | 04-26-2010 11:29 AM |