#1
|
|||
|
|||
changing one activity in a baseline
Hi
After saving my baseline, I realized that there was an activity that was not in my schedule before. So I added that activity but now for my baseline columns, it is showing as n/a for that activity. Can I simply add dates and durations to that activitys baseline column so include it in the baseline I already saved or are there any negative consequences of doing this? |
#2
|
|||
|
|||
The baseline for the summary tasks will not include the newly added task. You can baseline just that task as needed.
|
#3
|
|||
|
|||
How can I baseline just one task?
|
#4
|
|||
|
|||
Select the task first. Then Tools > Tracking, Save Baseline for selected tasks.
|
#5
|
|||
|
|||
Quote:
so can i make this task part of baseline i saved yesterday? how? |
#6
|
|||
|
|||
The only way to add the task to the baseline is to re-baseline any summary task with the new task.
You may wish to save a new baseline (baseline1) to have different baselines for comparison. |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
updating a delayed activity | ketanco | Project | 3 | 01-26-2012 01:47 PM |
some work was complete at my baseline | ketanco | Project | 1 | 01-25-2012 02:45 PM |
change color of critical activity texts | ketanco | Project | 3 | 01-05-2012 06:36 PM |
Retrieve a baseline after it's been cleared | fridos | Project | 2 | 05-11-2011 10:08 AM |
Help with Interim Baseline Variance | poyns | Project | 1 | 05-27-2010 10:59 AM |