JulieS JulieS is offline some work was complete at my baseline Windows 7 64bit some work was complete at my baseline Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

There is no baseline % complete field. I'd just add a note to the task. If the task was started when you baselined then Baseline Start = Actual Start.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
some work was complete at my baseline baseline duration of summary not updating. why ketanco Project 1 12-14-2011 09:07 AM
some work was complete at my baseline % Complete (Actual) vs % Complete (Should) Carlos Maximo Project 3 12-06-2011 12:01 PM
some work was complete at my baseline Retrieve a baseline after it's been cleared fridos Project 2 05-11-2011 10:08 AM
some work was complete at my baseline Help with Interim Baseline Variance poyns Project 1 05-27-2010 10:59 AM
some work was complete at my baseline In Outlook 2003 auto complete won't work Meenie Outlook 2 06-11-2009 08:24 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:49 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft