#2
|
|||
|
|||
|
Hello Antares,
1. Tasks with constraints other than ASAP or ALAP have icons appearing in the Indicator column. 2. You can apply the "Task with Fixed Dates" filter to see all tasks which are constrained. 3. You can add the Constraint Type field to a table view. I hope this helps. Julie |
|
|