ketanco ketanco is offline Adding or removing activities after basline Windows 7 64bit Adding or removing activities after basline Office 2007
Expert
Adding or removing activities after basline
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default Adding or removing activities after basline


I have a very basic question. When you make your first schedule enter your costs and resources etc you save the baseline and then later you can compare with actuals which I understand. But what if after saving your baseline, you delete or insert activities? Or change the relations between activities? How do you compare your new schedule to baseline and how can you perform earned value analysis in that case, (if you can do it at all)?
Reply With Quote
  #2  
Old 01-16-2012, 07:23 AM
JulieS JulieS is offline Adding or removing activities after basline Windows 7 64bit Adding or removing activities after basline Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Usually when adding new tasks, the discussion becomes whether to re-baseline or not. You can save multiple baselines and then select which baseline to use to EV calculations.
Reply With Quote
  #3  
Old 01-16-2012, 08:51 AM
ketanco ketanco is offline Adding or removing activities after basline Windows 7 64bit Adding or removing activities after basline Office 2007
Expert
Adding or removing activities after basline
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

Ok so in other words, you are saying that when we add or delete activities or change relations, the previous baseline inherently will not be apples to apples with the new actual sitation if we tried to use the same baseline, so you are saying we should make a new baseline in that case? I am just trying to understand if technically this is absolutely necessary or it is just a matter of preference. Which is technically the correct way I mean….
Reply With Quote
  #4  
Old 01-25-2012, 06:43 AM
JulieS JulieS is offline Adding or removing activities after basline Windows 7 64bit Adding or removing activities after basline Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Baselines data is saved when you save the baseline. If you add tasks after baselining -- there will be no baseline data for the added tasks. If you delete tasks after baselining - the baseline data for that task is deleted, however the summary task baseline does not change.

Again, re-baselining is usually negotiated between the Project Manager and Sponor(s). If you are adding new tasks are they enough to warrant a change order and rebaseline? If you are deleting tasks are you changing project scope and requirements?
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Adding or removing activities after basline Removing tabs Taylor Word 10 11-28-2011 03:38 PM
Removing Custom XML Ulodesk Word 0 06-24-2011 09:01 AM
Link activities and milestones between projects (2003) jowian Project 0 11-25-2010 09:10 AM
OL 2010 Public Contact Activities ibstech Outlook 0 08-05-2010 10:25 AM
Removing All Formating basscarp Word 0 01-31-2010 05:49 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:52 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft