lukusm lukusm is offline How to set task to be done by 4 resources each one after another? Windows 7 64bit How to set task to be done by 4 resources each one after another? Office 2010 32bit
Novice
How to set task to be done by 4 resources each one after another?
 
Join Date: Jan 2012
Posts: 1
lukusm is on a distinguished road
Question How to set task to be done by 4 resources each one after another?

Hello, my name's Lucas, I'm new user of this forum from Poland.



I'm trying to learn a lot about Ms Project and few days ago I found a problem, I cannot solve till today.

I have an exercise to do small project (building a car garage). And one point of this project is problematic: I don't know how to set the following situation - I have 4 employed bricklayers working on the construction field. And one of the task is "8h long, 4 bricklayers working, please set each bricklayer to work after another" - so each of them have to work for 2 hours, and next one starts his job when another will finish it (single work). If I only add them as resources to task, each of them will work full time (4 employees work together for 8 hours).

Does anybody have a solution for this problem? Any help will be appreciated.
Reply With Quote
  #2  
Old 01-16-2012, 07:21 AM
JulieS JulieS is offline How to set task to be done by 4 resources each one after another? Windows 7 64bit How to set task to be done by 4 resources each one after another? Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hello,

There are a couple of options:
  1. Create a summary task with 4 subtasks linked Finish to Start -- each 2 hours in duration. Assign 1 bricklayer to each of the 4 subtasks. Summary task duration will be 8 hours - total work will be 8 hours.
  2. Create a single task and assign the 4 resources. Split your screen (View Ribbon, uncheck the Timeline and check the Detail). Format the Task Form in the lower pane to Schedule. Add 2 hours delay, 4 hours delay, and 6 hours delay to the second, third, and fourth resource.

I hope this helps.
Julie
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Resources allocation walken Project 0 10-31-2011 04:32 AM
How to set task to be done by 4 resources each one after another? Setting up resources icw Project 2 09-04-2011 03:55 AM
how to make the task starts next day if no time enough today(task can not be split) duraid Project 1 10-25-2010 08:31 AM
How to set task to be done by 4 resources each one after another? Total Resources 602chrislys Project 1 10-04-2010 09:04 AM
Shared resources ediez Project 0 08-18-2010 12:04 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:29 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft