several task must be completed out of hours, not split
 
Join Date: Jan 2012
Posts: 1
proj is on a distinguished road
Default several task must be completed out of hours, not split

I have to update a large number of devices, each during out of hours. I have a couple of weeks to do this so I want to do as many per night as possible, however I cannot do more than one at a time.
To do the upgrade there are 3 tasks that have to run sequentially on each device and it has to be completed out of hours. How can I make project not start a device upgrade if it cannot complete all three tasks during the out of hours window?
Reply With Quote
  #2  
Old 01-13-2012, 08:38 AM
JulieS JulieS is offline several task must be completed out of hours, not split Windows 7 64bit several task must be completed out of hours, not split Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Ii would create a task calendar to restrict the working hours to your "out of hours" time. Unfortunately there is not a direct method to restrict tasks from not being split over the different "out of hours" slots. The best thing I can suggest is to figure out what is the required path -- ie can one task be done one night and the other two happen another night? Then see if you can estimate how long each combination takes. If the series of 3 tasks take a total of 4 hours and your "out of hours" time ends at 11:00 pm -- then it must be started by 7:00 pm in order to finish by 11:00 pm.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
several task must be completed out of hours, not split Task cannot stop once started, but cannot continue into non-work hours sullied Project 3 12-05-2011 06:32 PM
Split a task fridos Project 2 05-30-2011 11:19 AM
how to make the task starts next day if no time enough today(task can not be split) duraid Project 1 10-25-2010 08:31 AM
Need help with user-completed letter Rhazdel Word 0 09-10-2010 10:59 AM
How do i implement learnings from completed projects? stingy Project 0 03-18-2010 02:09 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:58 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft