Adjusting All Durations by 10%
I am a home builder and every project create 3 schedules for one project. The 100% (actual planned time), 110% (schedule I show the client), and 90% (schedule that I ask my PM to shoot for).
Is there an easy way to adjust the 100% schedule larger or smaller by 10% w/o adjusting every tasks duration and w/o losing the original 100%? |
#2
|
|||
|
|||
Hi,
Not directly. You can use some custom fields (Duration1, Duration2) and create a formula to write a formula and show the longer and shorter durations. You could then either copy/paste the new calculated durations over the duration field - and then re-draw the Gantt chart. let me know if you need more information or details. Julie |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Milestone durations | fraserm | Project | 4 | 01-13-2012 08:43 AM |
Task and Summary Durations | JR_12 | Project | 0 | 10-15-2011 05:07 PM |
Can't change period when adjusting actual time in Web Access | chip_saffire | Project | 0 | 10-04-2011 12:05 AM |
Calculate slide durations for song | hb2010 | PowerPoint | 1 | 10-19-2010 06:41 AM |
Adjusting Tabs | erselking | Word | 1 | 10-23-2008 02:57 PM |