calendar -reduced working hours
 
Join Date: Dec 2011
Posts: 12
pm_newbie is on a distinguished road
Default calendar -reduced working hours

Hello,
Just trying to get my head round calendars.
My first task is of 4 weeks length. With the default project calendar applied ie 40 Hrs a week.

So to check I know how to alter a calendar.
I change the duration to 120h and the task duration changes to 3 weeks (monday to fri X3).
Then I create a short week calandar (short week) of a 5 hour day/25 h week.
And change the applied calendar to "short week".
Save the project.
And reload.
I still have a 120h 3-week task.
Have I overlooked something?

TIA
Reply With Quote
  #2  
Old 01-07-2012, 06:22 AM
JulieS JulieS is offline calendar -reduced working hours Windows 7 64bit calendar -reduced working hours Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Do you have resources assigned to the task? If you have resources assigned, it is the resource calendar in "charge" on a task -- unless when you assign the task calendar you select the option "Scheduling ignores resource calendars."

Julie
Reply With Quote
  #3  
Old 01-09-2012, 12:24 PM
pm_newbie pm_newbie is offline calendar -reduced working hours Windows 7 64bit calendar -reduced working hours Office 2010 64bit
Novice
calendar -reduced working hours
 
Join Date: Dec 2011
Posts: 12
pm_newbie is on a distinguished road
Default

No resource appled yet.
I am however pleased to learn about the "Scheduling ignores resource calendars." option!
Thanx.
Reply With Quote
  #4  
Old 01-13-2012, 08:22 AM
JulieS JulieS is offline calendar -reduced working hours Windows 7 64bit calendar -reduced working hours Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi PMNewbie,

If you don't have resources assigned then either the Project Calendar (set in Project Information) or a task calendar is "ruling" the schedule.

So, a couple of questions:
Where/how did you change the calendar?
Did you create a new calendar or modify the "Standard" calendar.
I'm guessing you applied a task calendar?
What version of Project are you using? You are working with Automatically scheduled tasks?

Changing the calendar should not change the duration of 120 hours -- but it definitely will change the end date.

I hope this helps.
Reply With Quote
  #5  
Old 01-16-2012, 11:42 AM
pm_newbie pm_newbie is offline calendar -reduced working hours Windows 7 64bit calendar -reduced working hours Office 2010 64bit
Novice
calendar -reduced working hours
 
Join Date: Dec 2011
Posts: 12
pm_newbie is on a distinguished road
Default

Hi Julie,
Thanx for your continued interest!Double click on Task ie task information.
Advanced -> calendar-> Assign "Short week"
Ceated new calendar. 25 hrs per week
Not sure if I creatred a task calendar - it is described a base calendar.
project 2010 - yes auto.
Reply With Quote
  #6  
Old 01-16-2012, 01:43 PM
JulieS JulieS is offline calendar -reduced working hours Windows 7 64bit calendar -reduced working hours Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

If you press F9, does the finish date change?
Reply With Quote
  #7  
Old 01-17-2012, 09:55 AM
pm_newbie pm_newbie is offline calendar -reduced working hours Windows 7 64bit calendar -reduced working hours Office 2010 64bit
Novice
calendar -reduced working hours
 
Join Date: Dec 2011
Posts: 12
pm_newbie is on a distinguished road
Default

Hello Julie,
F9 did not help.
But I created a new Calendar (again) with the required working hours.
And it now works just fine.
I suspect that I had done something wrong when creating the calendar teh first time.
Thanks for your help.
Appreciated
;-)
And I will remember F9, which google tells me, forces recalculation!
Reply With Quote
  #8  
Old 01-17-2012, 10:34 AM
JulieS JulieS is offline calendar -reduced working hours Windows 7 64bit calendar -reduced working hours Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome. It sounds like things may have been off in the other calendar. I'm glad you have it sorted and thanks for the feedback.

Julie
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Actual working hours per day climbatron Project 2 12-17-2015 03:13 PM
calendar -reduced working hours How to add hours together PomDave Excel 3 09-05-2011 04:43 AM
calendar -reduced working hours 2007 Calendar - How do I show "working offsite" but available for phone meetings? Stan Outlook 2 08-16-2011 09:30 AM
calendar -reduced working hours Date and time calcs excluding non-working hours mrsatchmo Excel 1 01-26-2011 08:50 AM
emailed outlook calendar not working Tankerman Outlook 0 12-08-2010 10:36 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:39 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft