ketanco ketanco is offline free slack changes when i paste from fixed cost to cost1 column Windows 7 64bit free slack changes when i paste from fixed cost to cost1 column Office 2007
Expert
free slack changes when i paste from fixed cost to cost1 column
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default free slack changes when i paste from fixed cost to cost1 column


My schedule is based on a previous similar project, where I had copied the file, renamed it and made all necessary adjustments to durations relations and inserted and deleted activities etc…. now I am about to assign lump sum costs. Also in the previous jobs schedule, I had assigned fixed costs to activities, and now those fixed costs are still like the old projects costs. Now I will erase all the fixed cost column and will enter costs from scratch. However before doing that, in order to still see the old costs, I inserted a new cost column, cost1, and I started pasting the old costs to that one, so that when I erase the costs in the fixed cost column, I still see them on the side and can get a reference point in my head. But a strange thing happened when I pasted from fixed cost column to cost1 column and for some reason the free slacks of just some of the activities changed. I could not make any correlation as far as they are the new activities or old ones or summary or critical or what else….. just some activities free slack changed, although only thing I was doing was pasting from fixed cost column to cost1 column. Why did this happen and how can I prevent it? All my purpose is to paste the old job’s costs into cost1 and delete everything else and start assigining lump sum costs to my schedule. Note: I checked the resource sheet and there is nothing in there, as all I did was to assign fixed lump sum costs anyway…
Reply With Quote
  #2  
Old 01-05-2012, 06:35 PM
JulieS JulieS is offline free slack changes when i paste from fixed cost to cost1 column Windows 7 64bit free slack changes when i paste from fixed cost to cost1 column Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Sorry, but given your description, nothing should have changed. Free slack is related to predecessor/successor information -- are you sure you haven't changed that data?

Do you remove all tracking data? Removing Actual Starts will change scheduled start and may affect link relationships.

If truly all you have done is copied from the Cost field to Cost1 (no copying dates etc) then you should not be seeing any changes in schedule.

Julie
Reply With Quote
  #3  
Old 01-16-2012, 06:30 AM
ketanco ketanco is offline free slack changes when i paste from fixed cost to cost1 column Windows 7 64bit free slack changes when i paste from fixed cost to cost1 column Office 2007
Expert
free slack changes when i paste from fixed cost to cost1 column
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

i have no idea why this is happening. i dont think sending any screenshot will help it seems completely random. I paste costs and at totally different activities, the free slacks change
Reply With Quote
  #4  
Old 01-16-2012, 06:57 AM
JulieS JulieS is offline free slack changes when i paste from fixed cost to cost1 column Windows 7 64bit free slack changes when i paste from fixed cost to cost1 column Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

This is certainly not usual behavior. Re-using a project file which may have actual data may be causing the issue.

A couple of suggestions:
  • Ensure you are up to date on all service packs and cumulative updates.
  • Try repairing any corruption in the file. Save as XML and then import the data.
Again, working with spare Cost fields should not have any effect on the schedule. Do you see date/time data changing?

If you open the file, press F9 to force a recalculation and then copy/paste do you see any changes?
Reply With Quote
  #5  
Old 02-02-2012, 08:50 AM
ketanco ketanco is offline free slack changes when i paste from fixed cost to cost1 column Windows 7 64bit free slack changes when i paste from fixed cost to cost1 column Office 2007
Expert
free slack changes when i paste from fixed cost to cost1 column
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

it even did the same kind of thing when i inserted a notes column and pasted a single cell of text from text1 column to the notes column for the same activity!! how can i repair the corruption in the file? (how can i save as XML and import the data?)
Reply With Quote
  #6  
Old 02-03-2012, 06:17 AM
JulieS JulieS is offline free slack changes when i paste from fixed cost to cost1 column Windows 7 64bit free slack changes when i paste from fixed cost to cost1 column Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Ketanco,

You can try saving as XML (File > Save As). And then open the XML file. However, that is no guarantee that it will work.

What you describe is not normal behavior and you may just be better off starting again.

Julie
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
entering values for a cost type resource ketanco Project 3 12-26-2011 09:25 AM
free slack changes when i paste from fixed cost to cost1 column Quick Click not fixed in SP3? implus it Outlook 2 11-09-2011 01:30 PM
free slack changes when i paste from fixed cost to cost1 column Need to search a column for a macth and return a result from a third column pdfaust Excel 2 02-03-2011 03:02 PM
Powerpoint + paste in image with fixed width erki PowerPoint 0 09-19-2010 11:23 PM
free slack changes when i paste from fixed cost to cost1 column Time now--fixed? markg2 Excel 1 09-19-2010 12:05 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:33 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft