#1
|
|||
|
|||
calculate multiple critical paths
i am trying to understand the meaning of multiple critical path. i obviously know the meaning of critical path but how can there be more than one? by definition isnt critical path only one? how come there are multiple?
|
#2
|
|||
|
|||
see:
http://office.microsoft.com/en-us/pr...001226069.aspx For each "path" without successors, the critical path is calculated for that path. |
#3
|
|||
|
|||
but i made sure in my schedule that everything other than the last task has a successor. so my project would not have multiple critical paths correct?
|
#4
|
|||
|
|||
You are correct.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
motion paths | Cath5000 | PowerPoint | 0 | 07-29-2011 10:59 AM |
Critical Path w/ 2 Calendars | AndreT | Project | 6 | 07-27-2011 11:22 AM |
Motion Paths with Rotation | PBone | PowerPoint | 4 | 01-13-2011 11:59 AM |
Motion paths and shrinking textbox | Brin | PowerPoint | 0 | 01-12-2011 10:04 AM |
HELP! Rebuilt box & IRM lock out of critical docs | markcal | Office | 0 | 04-25-2010 11:45 AM |