entering lump sum costs
i have a detailed schedule now and i want to enter lump sum amounts for each activity. what is the best way / practice? should i just enter them to the fixed cost column?
|
#2
|
|||
|
|||
I would use the Fixed Cost column if you do not need detailed information about what the cost break down is.
If you need detailed information, then create cost resources and assign the specific costs. |
|