Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 12-23-2011, 11:36 PM
ketanco ketanco is offline entering values for a cost type resource Windows 7 64bit entering values for a cost type resource Office 2007
Expert
entering values for a cost type resource
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default entering values for a cost type resource

Hello,
I tried to enter cost resources and I am able to enter dollar amounts for rated and material costs, however there us a 3rd type, called cost resource i can not enter any values. later i discovered that you assign a cost to it by going into separate activities but everytime you need to assign value to it again. is there a way to assign a cost to a cost type resource and it can be used with the same cost for all activities? or is it not necessary? because that is covered by the material type cost?
Reply With Quote
  #2  
Old 12-24-2011, 12:51 PM
JulieS JulieS is offline entering values for a cost type resource Windows 7 64bit entering values for a cost type resource Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi Ketanco,

The purpose of a cost resource is to allow you to keep track of costs such as airline travel, hotels, etc. If there is a set cost per item, a material resource may be more useful.

Julie
Reply With Quote
  #3  
Old 12-24-2011, 05:15 PM
ketanco ketanco is offline entering values for a cost type resource Windows 7 64bit entering values for a cost type resource Office 2007
Expert
entering values for a cost type resource
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

so then a material cost may not necessarily be a construction material, but can be cost of anything, as long as its cost is fixed throught all its use right? so this means the cost resources will always have to be edited per each item correct?
Reply With Quote
  #4  
Old 12-26-2011, 09:25 AM
JulieS JulieS is offline entering values for a cost type resource Windows 7 64bit entering values for a cost type resource Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Material resources are assigned to tasks and you may enter a number of units of the material. Yes, it can be construction material or it can be reams of paper.

Both cost resources and material resources are edited at the assignment level. Split your screen from the Gantt chart to show the Task Form at the bottom and edit from there.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
entering values for a cost type resource entering future dates for a project that has started ketanco Project 5 12-15-2011 07:16 PM
entering values for a cost type resource Excel not entering numbers correctly weety Excel 2 06-29-2011 01:07 AM
Entering a postal bar code Sistafatti Word 0 07-14-2010 02:58 PM
Entering Contact details GemmaD Outlook 0 12-18-2008 06:41 AM
Automatically entering/fill data in cells in Excel 2003 dipdog Excel 0 08-17-2006 08:37 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:09 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft