#1
|
|||
|
|||
overallocated column
I had a resource which was overallocated but when i inserted a column called overallocated, it showed as no, even for the activities that the resource was overallocated. why was that?
|
#2
|
|||
|
|||
The overallocated field added to a task view simply notes whether the resource is assigned above their maximum units to that task. For example, you have Resource1 max units 50% and you have that resource assigned to a single task at 55%. The Overallocated field will show "yes".
Julie |
#3
|
|||
|
|||
how can i assign a resource % specificallly to a task though? i couldnt see it where. i clicked on the resource for that task but there is nowhere showing it
|
#4
|
|||
|
|||
In the Task Form at the bottom is the best method of assigning resources and viewing assignment units.
|
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
word column | irmorteza | Word | 2 | 07-05-2011 02:40 AM |
Need to search a column for a macth and return a result from a third column | pdfaust | Excel | 2 | 02-03-2011 03:02 PM |
Combo Box in whole column | ioustinos | Excel | 1 | 09-01-2010 01:24 AM |
Column width | markg67 | Word | 2 | 06-07-2010 07:40 PM |
Last Number in a Column | paulrm906 | Excel | 1 | 12-05-2008 07:51 PM |