Default Duration didn't copy to Baseline Duration when I saved a Baseline

I created a schedule and entered task names, durations, and logic (predecessors/relationships) and saved the schedule. At a later date, I set a baseline. When I started adding columns to the Tracking Gannt view, it appeared that no Baseline information was copied over.

If I understand the previous answer, the Baseline Duration column should have been populated with the information that I had already entered in the Duration column, correct? Is there a way to make Project copy this information over?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Baseline versus actual data Plas Project 1 12-16-2015 09:35 AM
How to create statis Baseline date columns baseline duration of summary not updating. why ketanco Project 1 12-14-2011 09:07 AM
how to create two columns based on a certain criterior from the original two column? where_pc Excel 3 06-13-2011 10:39 AM
How to create statis Baseline date columns Retrieve a baseline after it's been cleared fridos Project 2 05-11-2011 10:08 AM
How to create statis Baseline date columns Help with Interim Baseline Variance poyns Project 1 05-27-2010 10:59 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 07:40 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft