#1
|
|||
|
|||
baseline duration of summary not updating. why
hello. i have several activities and a summary line which contains all of them. when i update the baseline start and basline finish of the individual activities, the summary line basline start and basline finish cells do not update by itself. why? (and the project is in auto calculation mode. ) |
#2
|
|||
|
|||
The baseline dates from an updated subtask do not roll up unless you select that option when you create the baseline.
Julie |
|