#1
|
|||
|
|||
Timeline?
Office '07
Without spreadsheet knowledge heroics-- Is there a reasonably easy way to create on a single row a date defined start and finish with the intervening cells representing the consecutive weeks between the start and finish? Thanks, Mark |
#2
|
||||
|
||||
Hi Mark,
If you input the starting date in A1, then the formula =A1+7 in B1, you can copy that formula/cell across as far as needed. Each cell's date will be 1 week greater than that of the cell before it. Change the date in A1 and the date in all the other cells will change too.
__________________
Cheers, Paul Edstein [Fmr MS MVP - Word] |
#3
|
|||
|
|||
Thanks Paul!
Mark |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
[Office]How to create project timeline similar to this? | Coderedpl | Project | 0 | 09-11-2009 01:23 PM |