I want to add 15 days to date. After adding 15 days to a date, if the date is under (holiday list, Saturday & Sunday) then final date should be next working day. I tried this "=WORKDAY(A2,15,B$3:B$6)", A2= starting date 15 =number of days to add B$3:B$6= holiday list. but this omits the Saturday's & Sunday's from the begning itself. what i need is Saturday and Sunday need to included., if in case the final date comes under Saturday/Sunday/Holiday then the result should be next working day Thanks in advance. |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
Xaand | Word | 9 | 09-29-2023 11:38 AM |
![]() |
neon4 | Word | 7 | 01-21-2016 02:21 PM |
![]() |
dlowrey | Excel Programming | 3 | 05-12-2013 08:30 PM |
![]() |
Lights | Excel | 5 | 04-18-2012 04:31 AM |
calculation of start date | ketanco | Project | 1 | 02-29-2012 07:01 AM |