Hi,
I want to add 15 days to date. After adding 15 days to a date, if the date is under (holiday list, Saturday & Sunday) then final date should be next working day. I tried this "=WORKDAY(A2,15,B$3:B$6)", A2= starting date 15 =number of days to add B$3:B$6= holiday list. but this omits the Saturday's & Sunday's from the begning itself. what i need is Saturday and Sunday need to included., if in case the final date comes under Saturday/Sunday/Holiday then the result should be next working day Thanks in advance. |
#2
|
|||
|
|||
![]()
In attached file is a possible solution.
NB! It's better to leave the Weekday() function with European format - much easier for calculations when weekends are days 6 and 7. PS. Without additional sheet it will be nearly impossible. You must move the date away from weekend, then move away from holiday when date happens to be one, then again you have to check that new dates aren't weekends and when , then move the date, then you have anew to check for holidays, etc. |
#3
|
||||
|
||||
![]()
If you have a post 2007 version look at the NETWORKDAYS.INTL function
If not their are tons of solutions out there
__________________
Did you know you can thank someone who helped you? Click on the tiny scale in the right upper hand corner of your helper's post |
#4
|
|||
|
|||
![]() Quote:
Thanks for your reply.... It's working fine ![]() |
![]() |
Thread Tools | |
Display Modes | |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
neon4 | Word | 7 | 01-21-2016 02:21 PM |
![]() |
Xaand | Word | 7 | 02-21-2014 09:15 PM |
![]() |
dlowrey | Excel Programming | 3 | 05-12-2013 08:30 PM |
![]() |
Lights | Excel | 5 | 04-18-2012 04:31 AM |
calculation of start date | ketanco | Project | 1 | 02-29-2012 07:01 AM |