![]() |
#7
|
|||
|
|||
![]()
Thanks, I was just tinkering and discovered, our third shift starts the day, so our day schedule is for example
What I need to do is place a start date the line will run, the shift it starts, and the number of shifts it takes to complete - not factoring in lunch (shifts are 8 hours) and should be calculated as such. The end result will be the day and time (next shift in sequence) the part should be loaded on to the line. I know this sounds like a production schedule, but it isn't... I don't need anything that complex. Example... our schedule is done as 3rd shift as the start of the day, so if I start at 11pm (23:00) on day A 9/5/12 and end 9/7/12 at 11pm so the next run will be 9/8/12 7am (first shift) so I ran for 7 shifts. 9/5 - 3rd (11pm) 9/6 - 1st (7am) and 2nd (3pm) 9/6 - 3rd (11pm) 9/7 - 1st (7am) and 2nd (3pm) 9/7 - 3rd (11pm) (7shifts - each shift is 8 hours) 8/1- 1st (7am) - this shift is the start of next part I have attached the file itself. This is the formula I am using in cell C6 - =A2+B3+((A6)/24) thanks Last edited by freeman; 09-10-2012 at 02:01 PM. |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
sanlen | Project | 1 | 06-25-2012 04:17 PM |
Calendar work days in advance | paol:o | Outlook | 4 | 05-27-2012 07:23 PM |
Set calendar alarm x days before end date | el_ja | Outlook | 2 | 01-19-2012 10:09 AM |
Outlook Calendar continually resets days in Day View | tecsi | Outlook | 0 | 08-11-2010 06:45 PM |
Noob questions | punktilend | Word | 0 | 07-24-2009 02:41 AM |