I don't have an indicator field. I hid it and the % complete column because I don't use them. I don't know if setting a baseline will help me because my manpower, resources and durations are different for each subtask. is there a way to set individual subtasks with specific resource information so that when I create a new one it automatically assigns manpower (number1) duration and projected cost?