Thread: [Solved] Night shift and Day shift
View Single Post
 
Old 05-09-2016, 06:32 PM
JulieS JulieS is offline Windows 7 64bit Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

The easiest method would be to create the night calendar and assign it to resources who work nights. If then assign those resources to tasks - the tasks will shift to align with their calendars.

Take a look at the built-in Night Shift calendar as an example of calendars that span over mid-night. Let's say your schedule is 11:00 pm - 7:00 pm starting Sunday night.
For Sunday the working hours would be 11:00 pm - 12:00 am.
Monday 12:00 am - 7:00 am
11:00 pm - 12:00 am

The pattern established for Monday would run through Thursday morning.

You'd also need a "day shift calendar" from 6:00 am to 6:00 pm Monday through Friday. Assign that base calendar to resources who work days.