Night shift and Day shift
Hi guys,
I have a query, i am programming some construction works and we are permitted to work at night and during the day. Of a night we are able to work Sunday Night through to Thursday morning (Wednesday night/Thursday morning). Of a Day we are working from Monday to Friday with normal hours of 6AM to 6PM. My issue is that i want to show my night works and day works in the same program, how do i make a calendar for the night shift that runs from Sunday to Thursday morning and not have all my day works instantly start working on Sunday, can i assign the night shift calendar to resources and do it that way? is so how?
Any help greatly appreciated.
Cheers.
|