Start & Finish Date/Time
View Single Post
04-05-2016, 06:13 AM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
What is the duration of the Project Summary task - line 0. Without any tasks the duration should be zero and start date/time = finish date/time
JulieS